Updates - Congaree River

*August 19, 2022 

Over the last month, Dominion Energy has:

  • Completed the rock cofferdam for Area 1
  • Started armoring the cofferdam with a concrete injected liner to provide additional strength in the event of an overtopping

Next, Dominion Energy will:

  • Drain the entrapped water
  • Relocate mussels from the dammed area 
 Finished Cofferdam Aerial Image

 

Armoring cofferdam in process

 

up close shot of the cofferdam being armored

 


*July 14, 2022 

Over the last few weeks, the contractors have been installing the Area 1 cofferdam. Working from both the north end and the south end of Area 1, they were able to meet in the middle to form the footprint for the Area 1 cofferdam. They will continue to raise the level of the cofferdam and conduct other related activities over the next week. In a couple of weeks, they will start a process to armor the cofferdam so it will be able to be overtopped in the event of flooding conditions in the river. They will also be relocating mussels from the area blocked off by the cofferdam.

Congaree Update - Cofferdam Connected

 

Congaree Update - Cofferdam Connected2

*June 23, 2022

Landside setup operations have been completed. The Unexploded Ordnance Team from Tetra Tech has completed clearing the Area 1 and Area 2 cofferdam footprint from any Civil War era munitions. Cofferdam construction for Area 1 began on June 20, 2022. Cofferdam construction for Area 1 is expected to take about 5 weeks followed by 4 weeks for the cofferdam to be reinforced and armored.  

Cofferdam A with Bulldozer

cofferdam and dump truck

Cofferdam with Excavator

Congaree - Cofferdam PM


*June 8, 2022

Landside setup operations continue at the site.  Installing fencing around the site, completing the access roads for the Area 1 cofferdam, installing security cameras, and setting up staging areas for cofferdam stone have been top priorities.  

The Unexploded Ordnance Diving Team from Tetra Tech arrived this week and will begin clearing the Area 1 cofferdam footprint from any Civil War era munitions.  If the weather is good, this process should take about two weeks.  Once the cofferdam footprint is cleared, cofferdam construction will begin.  

Area 1 Access Road

 

Boat setting buoys

 

Sign with Partially Constructed Fence Behind

*May 26, 2022

On May 16, 2022, the contractor for Dominion Energy (Entact) mobilized off the end of Senate Street to set-up an operations area and begin installing:

  • Onsite routes for truck traffic; 
  • Utility poles for light and video surveillance;
  • Temporary office trailers; and
  • Fencing around the construction area.

Security of the site will be enforced 24 hours per day/7 days a week for the duration of the cleanup.

In early June, the contractor plans to begin stockpiling stone for the coffer dam construction. 

Congaree Sign
 

Congaree Land Side

Congaree - Sign with Site Behind

Congaree - Site Prep from Bridge

Tags

Pollution