Brenntag

Overview/History

The Brenntag Site consists of 8.9 acres containing a chemical warehouse, repackaging, and distribution facility located at 4200 Azalea Drive in Charleston, SC. From 1960 to 1997 the facility was owned and operated by Burris Chemical as a chemical warehouse and distribution facility. Since 1997, the majority of the facility property has been owned and operated by Brenntag. A 2-acre parcel that was originally part of the facility property was distributed to Burris Environmental Services and subsequently purchased by William M. Bird & Co. The Bird & Co. property contains an office building.   

Between 1975 and 1981, several large spills were reported to DHEC.  In January 1975 there was a fire in the former warehouse area. On August 31, 1978, a glacial acetic acid spill was reported. On July 2, 1979, a chemical called dimethylamine was spilled, and on July 10, 1981, there was a sulfuric acid spill. Numerous smaller spills and incidental releases are believed to have occurred. Since 1990 DHEC has worked with Burris Chemical, Burris Environmental Services, and Brenntag to investigate and clean up soil and groundwater at the Site. Soil and groundwater at the site are contaminated with petroleum hydrocarbons and chlorinated solvents. Two areas were initially identified for assessment and remediation.   

Preferred Clean-up Option

Area #1 groundwater is contaminated by chlorinated solvents.  Chemical amendments were injected underground to destroy the chlorinated solvent compounds in Area #1.  

Area #2 is contaminated by petroleum hydrocarbons and chlorinated solvents. Recent investigations have defined an area of heavily contaminated soil and groundwater in Area #2 on Brenntag's property. Due to issues related to off-site disposal of Area #2 soils, the removal originally planned for August 2022 has been delayed. This website will be updated when Area #2 remedial activities are rescheduled.

Area #3 was identified in 2021. This area is contaminated by chlorinated solvents. Area #3 includes an area of contaminated soil that will be removed and properly disposed of at an off-site disposal facility. The excavation will be backfilled with clean soil. Following the removal, additional actions are planned to clean up groundwater. These actions include injection of chemical amendments to break down contaminants (“in situ chemical reduction” or “ISCR”), and extraction of soil vapor and groundwater (“Aggressive Fluid Vapor Recovery” or “AFVR”). ISCR has been used at Area #1 and has shown very good early results. AFVR has been conducted in Area #2 to remove contaminant mass from soil and groundwater. This technology is commonly used to clean up fuel contamination at underground storage tank release sites.

Removal of soil from Area #3 is scheduled to begin on September 18, 2023. You may see and hear equipment and workers at the site during this time. The area to be excavated is shown in purple on Figure 10, below.  

The ISCR and AFVR actions will occur in the months following the excavation.  

Total volatile organic compound concentrations of the shallow aquifer measured December 15, 2021

*Figure 7 - Brenntag and adjacent properties. Areas 1, 2 & 3 are highlighted in pink. Numbers next to each monitoring well indicate the total concentration of volatile organic compounds in groundwater. 

Brenntag - Figure 10

*The green circles on Figure 10 represent the planned injection well points for ISCR.

Administrative Record

Date Title
February 17, 2023 Approval of Remedial Action Work Plan, Area #3
February 17, 2023 Request for a Removal Action, Area #3
December 8, 2022 Remedial Action Work Plan Area #3
July 6, 2022 Remedial Action Work Plan, Revision 1
April 6, 2022 Review of Second Semi-Annual 2021 Groundwater Report
April 5, 2022 Approval of Work Plan for Area #3
April 4, 2022 Work Plan for Area #3 Revision 1
March 30, 2022 Work Plan for Area #3
March 23, 2022 Second Semi-Annual 2021 Groundwater Report
September 30, 2021 Review of Additional Geoprobe Investigation
September 16, 2021 Additional Geoprobe Investigation
May 12, 2021 Work Plan for Area #2 - Generate at Remedial Work Plan for Area #2, Indoor Sampling, & Additional Geoprobe Locations
March 23, 2021 Review of Second Semi-Annual 2020 Groundwater Report
March 2, 2021 Second Semi-Annual 2020 Groundwater Report
February 2, 2021 Review of Results of 72 Hour AFVR
December 12, 2020 Results of 72 Hour AFVR
September 29, 2020 Conditional Approval - Work Plan for Area #2 Revision 1
September 28, 2020 Work Plan for Area #2 - Revision 1
September 10, 2020 Review of First Semi-Annual 2020 GW Monitoring Report
September 8, 2020 Work Plan for 72 Hour AFVR
September 3, 2020 Approval of Work Plan for 72 Hour AFVR
October 29, 2019 Response to DHEC Letter dated October 4, 2019
October 15, 2019 Corrective Action Plan - Soil & Water
October 4, 2019 Response to Letter Dated August 21, 2019 
August 21, 2019 Response to DHEC Letter & Follow Up to Meeting in Charleston 
July 24, 2019 Review of Groundwater & Soil Vapor Assessment Report
May 12, 2019 Groundwater & Soil Vapor Assessment Report 
August 31, 2018 Vapor Intrusion Assessment Plans
August 31, 2018 Conditional Approval - Groundwater Assessment Plan
August 30, 2018 Review of First Semi-Annual 2018 Groundwater Monitoring Report 
August 21, 2018 First Semi-Annual 2018 Groundwater Monitoring Report
July 31, 2018 Review of Semi-Annual Groundwater Monitoring Report
July 8, 2018 Semi-Annual Groundwater Monitoring Report
May 16, 2018 Extension of Submission Deadline for Work Plan
May 4, 2018 Review of Second Semi-Annual 2017 Groundwater Monitoring Report
April 16, 2018 Second Semi-Annual 2017 Groundwater Monitoring Report
October 30, 2011 Groundwater Monitoring & Response Plan
June 11, 2003 Work Plan to Evaluate Groundwater Quality