*May 26, 2022
On May 16, 2022, the contractor for Dominion Energy (Entact) mobilized off the end of Senate Street to set-up an operations area and begin installing:
- Onsite routes for truck traffic;
- Utility poles for light and video surveillance;
- Temporary office trailers; and
- Fencing around the construction area.
Security of the site will be enforced 24 hours per day/7 days a week for the duration of the cleanup.
In early June, the contractor plans to begin stockpiling stone for the coffer dam construction.